Everglades Restoration Webinars in August

    0
    7

    The U.S. Army Corps of Engineers, Jacksonville District is hosting two public virtual Integrated Delivery Schedule (IDS) educational webinars and stakeholder listening sessions on Friday, August 2nd at 3 p.m. and Friday, August 9th at 3 .m.

    The IDS reflects the sequencing strategy for planning, design, and construction for the South Florida Ecosystem Restoration Program. This is a living document that synchronizes federal and state program and project priorities to give us a clear path forward.

    The IDS is a forward-looking snapshot of upcoming design and construction schedules and programmatic costs at a “top” line level for the South Florida Ecosystem Restoration Program. It includes Comprehensive Everglades Restoration Plan (CERP) projects, and other non-CERP Everglades restoration efforts including Kissimmee River restoration, Tamiami Trail next steps, C-111 South Dade Project, and restoration strategies. Everglades restoration focuses on “getting the water right.” CERP—the largest aquatic ecosystem restoration effort in the nation, spanning more than 18,000 square miles — is designed to improve the health of more than 2.4 million acres.

    Questions and answers will be moderated virtually through the WebEx chat.

    Friday, August 2, 2024:
    3 p.m. to 5 p.m.
    https://usace1.webex.com/meet/tabitha.m.elkington
    US Toll Free +1-844-800-2712
    2760 169 3425

    Friday, August 9, 2024:
    3 p.m. to 5 p.m.
    https://usace1.webex.com/meet/tabitha.m.elkington
    US Toll Free +1-844-800-2712
    2760 169 3425
    Additional information is available HERE