New Boutique Hotel Will Take 4 Years To Build

    31
    2

    New Vice Mayor Tom Brady logged his first no vote, objecting to the Hideaway Village Resort at 5601 and 5607 Estero Boulevard. Brady said he was concerned about the “lack of defined public benefit” The project, which includes 30 units, was approved by a 4-1 vote.

    Now that the Town Council approved the project, the Development Order and permitting process is expected to take 12 to 18 months then it will take another 12 to 18 months to build. The Neighborhood Company’s Ken Gallander, representing the property owners, said realistically it will be 4 years before hte hotel opens its doors.

    The new boutique resort will include 30 units and up to 3,500 square feet of commercial space including a restaurant and retail. The total size of the property is .63 acres which is now an empty lot near the Woman’s Club property. The restaurant and a coffee shop will be open to the public.

    Before Hurricane Ian, the property included three buildings containing a 23-unit (22 guest units and a management unit) hotel/motel. The two-story buildings offered amenities such as kitchenette units, a swimming pool, outdoor dining areas, and on and off-site parking facilities for its guests. 

    In addition to increasing the number of units by 7, the proposal includes the restaurant and a coffee shop, a small sundries shop open to the public, and a rooftop pool for hotel guests only. 

    The ground floor will include primarily parking, back of house operations, hotel lobby, and small food service/retail (café/coffee/sundries shop). The second floor consists of a combination of restaurant area, hotel accessory uses, fitness center/back of house, and hotel guest units. The third floor will be primarily guest units, and the fourth floor will consist of guest units and hotel amenities such as the pool/amenity deck area and back of house operations.
    The CR zoning allows heights of three stories or 30 feet above base flood elevations. A deviation was requested regarding the height of the development, which is to allow a maximum of four stories and a maximum zoned height of 47 feet. The maximum actual height is 63 feet measured from grade to peak of highest roof. A total of 8 deviations were approved. 

    Local journalism is hard work. If you appreciate the most in-depth reporting on Fort Myers Beach, please support what we do HERE by Venmo, Zell or PayPal. Thank you.

    31 COMMENTS

    1. Completely agree with Dennis. I dont know much about this Vice Mayor Tom Brady except that he was a great quarterback and deflated the football….but not a fan already if he said no so quickly to such an obvious step forward.

    2. I have a home down the street and I cannot wait until this is done. So glad it was approved. Too bad it is not faster but I understand these things take time. 4 years will fly. We used to use the Hideaway all the time for friends and family. Glad they are coming back!!!

    3. I agree with Dennis Wagaman; keep discussions about the public benefit of these projects fair, reasonable, objective and limited. What is the public benefit of an empty lot?

        • It is not 18 months just to obtain permits. That estimate includes the considerable amount of work required to move the project from approval to construction. Now that the project has received land-use approval, the developer is moving forward with the detailed architectural plans, engineering, and construction specifications. This takes time, particularly with an irregularly shaped lot like this one, where the design requires additional coordination. A commercial project of this size involves much more than floor plans and architectural renderings. The team must work through the foundation design, structural connections, load requirements, roofing systems, drainage, utilities, and mechanical, electrical, plumbing, and fire-protection systems. These components must work together, meet applicable codes, and fit the approved design. At the same time, the team is evaluating material and labor costs, availability, and delivery schedules to keep the project within budget while maintaining the required quality and performance. The developer also needs pricing from qualified commercial contractors with the experience and resources to deliver the project on schedule and within budget. A contractor may be involved during design to help evaluate costs and identify potential construction issues. Once the required plans and supporting documents are ready, permit applications can be submitted. Permitting, contractor bidding, and final budget coordination can overlap. The point is that substantial design, engineering, and financial planning must take place before construction can begin, and permitting is only one part of that process.

        • It took just over 2 yrs from signing up with house builder to finish a 1500 sq ft house so it doesn’t surprise me a project like that would take twice as long.

    4. How much total parking is available on the property? How much should there have been per town code? Not everyone staying in the hotel or driving up to use the restaurant/cafe will have parking?

    5. I think it’s fair to point out that much of those first 18 months is typically spent by the developer preparing the actual plans for the project.

      What you’re seeing right now is a rendering, not a completed set of construction plans. Developers generally don’t invest the time and money into detailed plans for submission to the town until they have the necessary approvals.

      It doesn’t take 18 months for the town to review a project. In most cases, developing the plans takes considerably longer than reviewing them.

      Realistically, the town likely won’t even have detailed plans to review for at least another year. There’s a big difference between the time it takes to design a project and the time it takes the town to review it.

    6. And the new vice mayor is right, public benefits did not justify the 9 deviations, but most don’t understand this. Time is over for the public benefit loophole the developers have been abusing with the former council who allowed them to.

      • Replacing a vacant parcel with a beautiful boutique hotel, restaurant, and coffee shop will bring visitors, jobs, tax revenue, and walkable dining options for nearby residents. Are you aware that one of the deviations is necessary because that specific section of the Town’s current comp plan does not comply with current Florida building code? Yet too many who are not familiar with this detail will want to bash the “greedy developer”. This is a much-needed project in this location on the island, and it provides substantial public benefits. Residents have every right to ask questions and expect responsible development. But labeling developers as greedy overlooks the time, money, and risk involved in rebuilding our island. If “public benefit” has not been clearly defined, how can we fairly say this proposal falls short? What specific reasonable benefits are missing? We also need to recognize the consequences of pushing too far. If demands make the project unworkable and the developer walks away, is the community better off with another vacant property? We all have a stake in the island’s future. Let’s evaluate the proposals fairly, recognize what they offer, and keep the discussion objective and constructive.

        • I have said for a few years now that things HAVE changed after September 28, 2022. Keeping in mind these changes, the Town needs to update the comp plan to allow for a little more flexibility for developers. Don’t take this to mean I am for 17 story towers, but maybe allowing 4 or 5 floors over flood, and sticking to that will allow more development.

    7. It’s not the permit process that’s taking long. They said it in the presentation, 2 years for planning and 2 years of construction. Nothing is the towns fault. The permit process is simple IF you simply adhere to it.

      • Lance you’ve never had to deal with this process evidently. It’s the lack of staff that can handle all these projects. No fault of any one person. It’s just the sheer magnitude of permitting so many projects. It is lengthy due to this lack of enough resources.

    8. Lack of public benefit… Like paying real estate taxes and bringing in tourists who pay the tourist tax and fill restaurants is not a public benefit….Then one day they stop being a tourist and buy on the island for a permanent home….

    9. This whole permitting thing is ridiculous along with all the hoops these people have to jump thru to move forward. Let’s hope the 12 new FMB employees were hired for the permitting office. But that would make to much sense. It’s a bad system. Please fix it.

    10. Yet another large, empty, desolate lot for 2-3 more years. It’s time for the Town to figure out a way to fast track the permitting process! I was really excited about this project when you first shared it. How many years ago was that now?

    11. I’m just wondering why the permitting process takes so long? By the time these buildings are constructed, labor and materials costs have risen by 6% to 7% or more.