Starting today, and every Tuesday moving forward, we plan to give you an update on the Estero Boulevard road project. This week, contractors for the Town and Lee County are installing new water main, sanitary sewer force main, storm drainage, and sidewalk and rebuilding roadway on the Boulevard from Strandview Avenue/Publix to the south end of the island.

Two travel lanes are expected to remain open the majority of the project; however, motorists may experience daytime or nighttime one-lane traffic on Estero Boulevard. Flaggers will alternate traffic frequently, but motorists should expect delays. Motorists may also experience momentary delays while crews move materials for the construction activities. Crews are expected to work Monday through Friday and some Saturdays. Construction will be year-round. This schedule may change due to underground conditions and inclement weather. 

...

One Response to This Week on Estero Boulevard

  1. ltd says:

    Previous BTRN interview with Kaye Molnar stated segments 3 & 4 would be be completed by end of year 2020. They are still a work in progress, it would be great to get a new eta.

Leave a Reply

Your email address will not be published. Required fields are marked *